Intensive co-operation in development

 

Market screening for interesting technologies

Plant Geldern Screening of the market and of Unimicron portfolios for relevant technologies

 

Internal technology approval  1-3 years

Plant Geldern Evaluation and testing of new technologies; internal sample production.
Plant Kunshan Preparation of technology transfer.

 

Customer technology approval  1-12 months

Plant Geldern Evaluation by the customer; conjoint development of the customer-specific approval.
Plant Kunshan Approval usually with a time-shift

 

Product release  2-16 weeks

Plant Geldern   Plant Kunshan Production of C samples