17 May 2018

Unimicron Germany celebrates the opening of their new innerlayer plant

On Saturday, the 21st April 2018, exactly 479 days after the fire, the big day for Unimicron Germany arrived. With more than 800 guests, the opening of the new inner layer plant was celebrated.

The official part of the opening took place in front of the main entrance of the new innerlayer plant. In their speeches the CEO of the parent company from Taiwan, T.J. Tseng, the chairman of the supervisory board Lucien Orlovius and the CEO Gerard van Dierendonck, above all expressed their thanks to the employees and suppliers who helped to complete the construction in record time. Mr. van Dierendonck also thanked the authorities of the city of Geldern for their non-bureaucratic support during the planning, approval and realization of the new building. In his speech, the mayor of Geldern, Mr. Sven Kaiser, also mentioned the good cooperation during the planning and approval phase and emphasized the importance of the company for the region.

(From left to right: T.J. Tseng, Lucien Orlovius, Sven Kaiser and Gerard van Dierendonck cut the opening ribbon)

During the opening ceremony, the visitors had the opportunity to visit the new plant also from inside. Directly after the fire, Unimicron Germany started the planning phase for one of the most modern and sophisticated inner layer plants in Europe. Unimicron has invested around 45 million EUR in the new production facility, thereof 36 million EUR used for state-of-the-art machinery and equipment. As soon as the production ramp-up starts from May on, more complex printed circuit boards can be produced with the highest quality, while capacity will be increased by approx. 30%. Last but not least, the operation will become more environment-friendly. In the future, 90% of the chemicals used will be processed and reused in the factory. In the old factory, it was only 75% of the chemicals.

(Tour in the new innerlayer plant, plant manager Wolfgang Burgermeister shows all the technical innovations in the production to the visitors)
After the official part, the celebrations continued until late in the night. The musical highlight was the performance of the band “Brings”. Previously, the CEO Gerard van Dierendonck had a surprise for the mayor of the city in Geldern. Together with the suppliers, he had collected a total of EUR 32,500 for charitable projects.
(CEO, Mr. van Dierendonck hands over the donation check to the mayor of Geldern, Mr. Sven Kaiser) 

 

Further press comments regarding the rebuild and the opening ceremony:

DE

https://rp-online.de/nrw/staedte/geldern/unimicron-werk-vor-der-neueroeffnung_aid-17122193

https://rp-online.de/nrw/staedte/geldern/unimicron-startet-in-geldern-neu-durch_aid-18603243

https://evertiq.de/news/22256

EN

http://pcb.iconnect007.com/index.php/article/110315/unimicron-germany-rises-from-the-ashes-with-new-smart-factory/110318/?skin=pcb

https://evertiq.com/news/44012